Hu Honua
Hu Honua proposes to clear-cut forests, turn the trees into wood chips, and burn the wood to generate electricity. The Public Utilities Commission approved the HELCO-Hu Honua Power Purchase Agreement. The Hawaii Supreme Court remanded the case back to the Commission in May 2019.
The Commission re-opened the proceeding and asserted that Life of the Land could address all issues in the original proceeding, as well as the new issue involving lifecycle greenhouse gas emissions. The issues include financial cost, air pollution, and water pollution.
Gas Company
The Gas Company proposed importing fracked Liquified Natural Gas from Canada and the U.S. Continent. The Gas Company filed a rate case application. Life of the Land (LOL), Hui Aloha 'Aina O Ka Lai Maile Ali`i (KLMA), and 350 Hawai'i filed timely motions to intervene. The Commission`s decision ignored climate change issues.
Only LOL and KLMA appealed the Commission decision. The Hawaii Supreme Court remanded the case back to the Commission on June 9, 2020. The Commission will re-open the proceeding to address climate change, public trust, and Native Hawaiian issues.
GHG Analysis
Recognizing that the Commission must address climate change, the Hawaiian Electric Companies filed greenhouse gas analysis in Power Purchase Agreement proceedings: AES West Oahu Solar, MECO-Peaahu Solar, HELCO-Hu Honua, and HELCO-Puna Geothermal Venture; and also in HECO`s proposed acquisition of the U.S. Army`s Oahu Electric Distribution Systems, and HECO`s proposed East Kapolei II 12kv Overhead to Underground/Overhead Project.
Par Hawai`i
Par Hawai`i owns the only two
refineries in the State. One was formerly owned by Chevron and the other was
formerly owned by Tesoro.
Hawai`i informed the HECO
Companies that they must renegotiate their fuel contract quickly or be cut off
from receiving any fuel.
HECO,
MECO, and HELCO filed an application for approval of the First
Amendment to Petroleum Fuel Supply Contract with Par Hawaii Refining on June 9, 2020.
HECO`s filing stated, “Par’s demand places the Commission, the Consumer Advocate and the
Companies in a very difficult position requiring the negotiation and review of
the First Amendment on a very tight timeline.”
The filing was included in the Commission`s Daily Activity Report email blast sent out
on June 10th at 4:31 pm. The intervention window is 20 days. Life of the Land
filed a motion to intervene on June 11 at 7:25 a.m.
Hawaiian
Electric received a letter from Par alleging that it has a contractual right to
request a renegotiation of the existing Petroleum Fuel Supply Contract on April 29, 2020.
“Par contends that its request is based on dire financial impacts from the COVID-19 pandemic.”
“Par represents as follows: Impacts from the pandemic include a decrease in fuel demand resulting in historically low or negative margins on Par products. Specifically, government orders addressing the pandemic have had a significant economic impact on Par under the terms of the Contract, and the continued adherence to the Contract is creating significant financial hardship. The pandemic has resulted in drastically reduced ground and air travel throughout Hawai`i, the United States and the world.”
“The recent events
have had a direct impact on Par’s sales margin to Hawaiian Electric for the
LSEO under the Contract, which led to the shutdown of Par’s crude unit at Par
West on March 23, 2020. On March 25, Par announced production reductions and
turnaround deferrals. On May 5, Par implemented a furlough of 29 employees in
response to the decline in throughput rates at its refineries. Without Par
West, Par cannot sustainably locally produce the full volume of LSEO required
by the Companies and will have to import barrels of LSEO to meet demand.”
“While the [HECO] Companies dispute that Par has the
contractual right to demand renegotiation or justifiably terminate the
Contract, the Companies believe there is real and present risk that Par will follow through and terminate
the Contract, rightfully or wrongfully, in the timeframe stated.”
“Thus, while reserving all rights,
the Companies began negotiations with Par in an attempt to agree on a potential
Contract amendment and avoid protracted litigation and potential fuel supply
interruption that would materially impact and threaten the Companies’ ability
to continue providing service to its customers. Under the current economic and
emergency health and safety circumstances, the risk of fuel supply interruption
due to a contract dispute is simply untenable.”
“Aside from whether Par has a right to renegotiate or terminate the Contract, the Companies have no basis to dispute that Par is suffering significant negative economic impacts as a consequence of the pandemic.”
“The Companies believe that
approval of the First Amendment is in the best interests of customers, as it
will maintain a secure source of fuel for electricity generation with pricing
at or below alternative fuel procurement sources.”
“Par agreed to
lower the LSFO carbon residue specification from 15.0% to 12.0% under the First Amendment,
which under the current Contract would have added significant
cost. Carbon residue is important regarding the Companies’ compliance with the
Mercury and Air Toxics Standards.”
“Par has also
agreed to retain the existing prices under the Contract for those fuels other
than LSFO, provided Hawaiian Electric signs the First Amendment and the First
Amendment is ultimately approved by the Commission. Par represents that it
would otherwise cancel the entire Contract. The significance of this measure is
that the fuels for the neighbor islands will not be subject to new pricing if
Par and Hawaiian Electric reach agreement on, and the Commission approves, the
First Amendment.”
“In addition, the
First Amendment allows the Companies to give notice of termination of the LSFO
portion of the Par fuel supply contract by August 06, 2020, which gives the
Companies an opportunity to conduct an RFP to test the market for other LSFO
supply opportunities. A termination made pursuant to this opportunity would be
effective 120 days later or a date mutually agreed upon by both parties. The
Companies issued an RFP for LSFO on June 5, 2020 to evaluate potential LSFO
supply alternatives to the First Amendment.”
Life of the Land
Life of the Land filed a motion to intervene. HECO asserted that the fuel amendment does not need a greenhouse gas analysis. There are significant greenhouse gas emissions associated with the extraction of petroleum and its refining. Life of the Land desires a full greenhouse gas accounting of the different options available.
# #
#